Projects - Overhaul of Pha Lai thermal power plant in 2011

Overhaul of Pha Lai thermal power plant in 2011


Project Description

Provision of replacement and spare materials and equipment for  Pha Lai Thermal Power Plant Line 2.

PROJECT LOCATION:

Pha Lai Wards, Chi Linh Town, Hai Duong Province.

PROJECT TYPE:

Overhaul, maintenance and supply of equipment

PROJECT COST:

$2,312,900

CLIENT:

Vietnam Power Group - EVN

GENERAL PROGRESS
100%
Provide regular repair materials for system No.2
100%
Supply of thermal equipment and materials
100%
Supplying materials for overhaul of auxiliary equipment of turbine No. 6
100%
Supply of materials and equipment for the overhaul of the circulating water No. 6
100%
Supply of Turbine BOP
100%
Supply of Driver Pump and Control valve for driver pump
100%